They got a lot of work done yesterday. Reminder of the original schedule:
This called for 2 days of demo work, but they did it in one. Here is the look at the start of the Day 2:
Week 1 – (April 27 – April 28) Wednesday, Thursday Start time 9am:
- Demo: 2 Days
Dumpster did get delivered, and is still in the drive way.
Panoramic of the whole kitchen, looks like demo is DONE! So with starting a day early and demo only one day, we are already 2 days ahead of schedule, also notice (if you can see the holes with the outlet boxes in them, the rough electrical is complete.
So, looking at what is next on the proposed schedule:
Week 2 (May
2-May4): Monday, Tuesday, Wednesday, Thursday, Friday:
- Flooring: 3 Days
- Rough Electrical / Plumbing 3
days Today's mission: Stop the squeaks, add a firm pre-tile layer, and lay the tile. With the goal of grouting and finishing the floor tomorrow. Still keeping us about half a week ahead.
Detail of squeaky base floor layer:
We agreed upon 9 am for tomorrow.
Additionally, we spoke of a troublesome plumbing problem from upstairs, more on that later as that is next week's problem, and may put us back a day... or maybe not.
We also reviewed that there would be under cabinet and in cabinet lighting.
We also reviewed that there would be under cabinet and in cabinet lighting.