The first day of construction. Last night we learned they wanted to start today! So we had to empty all the cabinets last night.
The proposed Schedule:
Week 1 – (April 27 – April 28) Wednesday, Thursday Start time 9am:
- Demo: 2 Days
Here is what the kitchen looked like, at 9 am, clean and ready to be demolished.
We wrapped the living room and dining room to protect from dust.
I visited the building department to pick up the permit. that took longer than it should have with only one lady to answer the inspector, me, the phones...
I returned, the dumpster had not been delivered yet, but the appliances were in the garage, and a couple of the cabinets were already in the driveway.
So I went on to work.
So I went on to work.