Monday, April 25, 2016

Pre-Installation Meeting

Met with the Jennifer the designer from Lowe's and the contractor's supervisors.  We checked in all the deliveries. and discussed schedule.

Jennifer had suggested starting Wednesday, but the contractor said why wait, let's do it tomorrow!!

This means we have to work hard and pack up the kitchen TONIGHT!

Here is Jennifer's proposed schedule, still showing the start work on Wednesday.

Week 1 –  (April 27 – April 28)  Wednesday, Thursday Start time 9am:
- Demo: 2 Days

Week 2  (May 2-May4):  Monday, Tuesday, Wednesday, Thursday, Friday:
- Flooring: 3 Days
- Rough Electrical / Plumbing 3 days  

Week 3  (May 9-May13) Monday:
Monday – Conclusion of Rough Electrical and Plumbing
- Tuesday – Friday Hold for inspection   (Town determines this and we have very little control of what day they can send inspector)

 Week 4  (May 16-20th) Monday, Tuesday, Wednesday, Thursday, Friday:
- Finish Electrical Plumbing: 2 Days
-- Cabinet Install: 3 Days

Week 5  (May 23rd-May 26th) Monday, Tuesday, Wednesday, Thursday:
- Appliances/Misc. Items: 2 Days
Counter-top Measurement   (Amy and Barney to work with Patricio in Lowes install office to coordinate with counter-top vendor on scheduling the date; once your counter-top is measured, allow minimum 7 days for counter-top to be fabricated)

Week 6  (May 30th – June 3rd):
- Countertop installation  (Coordinate date of installation with counter-top vendor Stone Systems )
Back-splash

The kitchen should be complete by June 3rd, then week 7 and 8 are for final walk through based on everyone’s availability, including yours

Week 7  (June 6th – June 8th      OR June 13 – June 15):
- Final Inspection: Depending on the town's schedule and yours

- Lowes and GC team also do a final walk through once job is completed and hand over the certificate of completion 