Jennifer had suggested starting Wednesday, but the contractor said why wait, let's do it tomorrow!!
This means we have to work hard and pack up the kitchen TONIGHT!
Here is Jennifer's proposed schedule, still showing the start work on Wednesday.
Week 1 – (April 27 –
April 28) Wednesday, Thursday Start time 9am:
- Demo: 2 Days
Week 2 (May
2-May4): Monday, Tuesday, Wednesday, Thursday, Friday:
- Flooring: 3 Days
- Rough Electrical / Plumbing 3
days
Week 3 (May
9-May13) Monday:
Monday – Conclusion of Rough
Electrical and Plumbing
- Tuesday – Friday Hold for
inspection (Town determines this and we have very little control of
what day they can send inspector)
Week 4 (May 16-20th)
Monday, Tuesday, Wednesday, Thursday, Friday:
- Finish Electrical Plumbing: 2
Days
-- Cabinet Install: 3 Days
Week 5 (May 23rd-May
26th) Monday,
Tuesday, Wednesday, Thursday:
- Appliances/Misc. Items: 2 Days
- Counter-top Measurement
(Amy and Barney to work with Patricio in Lowes install office to
coordinate with counter-top vendor on scheduling the date; once your counter-top is measured, allow minimum 7 days for counter-top to be fabricated)
Week 6 (May 30th –
June 3rd):
- Countertop installation
(Coordinate date of installation with counter-top vendor Stone Systems )
- Back-splash
The kitchen should be complete by
June 3rd, then week 7 and 8 are for final walk through based on
everyone’s availability, including yours
Week 7 (June 6th –
June 8th OR June 13 – June 15):
- Final Inspection: Depending on
the town's schedule and yours
- Lowes and GC team also do a final
walk through once job is completed and hand over the certificate of completion