Construction: W1D3

They [almost] finished the tiles yesterday - they were short one.  They are grouting the tiles this morning!



Now to review last night's email from the contractor:

As you can tell by now, the demo is completed for your new kitchen and the tile is underway. We are estimating the tile will be completed and grouted tomorrow.

As ... discussed with you earlier today, after completing the demo of the soffit, we found plumbing that will need to be re-located in order to close up the walls. To do this, we need to apply for an additional subcode permit with the town.

...our office will be applying for this first thing in the morning, and we have asked the town to put a rush on approving the addition as soon as possible so that we can avoid waiting on the rough inspections.

Our plumber will be in contact with you in the next few days to schedule to complete the plumbing change order needed. After the plumbing is completed, we will not be able to return to proceed further with the project until the rough inspections pass.

We will have an update for you on Monday as to when these inspections are scheduled.

Well, that will bring the schedule to a grinding halt, and back in line with the estimate...

No more work until at earliest Tuesday [answer about permit late Monday].